Bring one current view of each engagement
Set the review period and prepare the same fields for every active engagement: agreed scope, planned hours, reviewed time used, remaining work, near-term deliverable and open decisions. Note when the figures were read. If time corrections or task estimates are still missing, mark that uncertainty instead of presenting an exact-looking forecast as settled.
Read the team updates before the meeting. Bring questions about an exception, such as a repeated dependency or an estimate that changed, rather than asking each person to recite the week. Work that is proceeding as expected can remain in the written record. Give discussion time to the changes that need a decision.
This is a project review, not the staffing calculation in the weekly agency capacity review. Use that companion guide when the decision is who can take the work. Here, the question is what the agency and client should do about the scope, forecast or delivery plan.
Compare remaining work with the current budget
In a fictional engagement, the agreed plan is 80 hours. The reviewed sheet shows 52 hours used. The remaining tasks are estimated at 36 hours, so the working forecast is 52 + 36 = 88 hours, eight hours above plan. That is a prompt to inspect the scope and estimates; it is not proof of wasted effort or a promise about the final result.
| Field | Hours | Question for the review |
|---|---|---|
| Current agreed plan | 80 | Does this include every accepted scope change? |
| Reviewed time used | 52 | Are corrections and classifications settled? |
| Estimated work remaining | 36 | Which tasks and assumptions support this? |
| Working forecast | 88 | What decision addresses the eight-hour gap? |
| Forecast above plan | 8 | Change scope, agree more work, or revise the approach? |
Suppose six of the remaining hours belong to a newly requested export format. If the client has not accepted that addition, keep it as a scope decision rather than quietly changing the baseline. The team might defer it, agree revised hours, or find a different solution. Record the choice and update the plan only when the responsible people have made it.
Use an agenda built around exceptions
- Delivery: what is ready for review, accepted or released, and what evidence supports that state? Keep those stages distinct.
- Remaining work: which task estimate or dependency changed since the last review? Include work waiting for a client answer.
- Budget: compare the current plan with reviewed time plus estimated remaining work. Explain the material gaps.
- Scope: list requested additions and identify who can accept, defer or reject them. Keep unapproved requests visible.
- Billing: identify manual time, corrections, unclassified work or client questions that could affect the next invoice.
- Capacity: send any changed staffing need to the capacity review, with the work and deadline attached.
- Decisions: assign one owner, next action and due date to each unresolved exception. Decide which changes the client needs to hear about now.
Set a threshold for discussion that matches the size of the engagement. A two-hour variance may matter on a short fixed engagement and be routine on a larger retainer. Use a written reason for the threshold so people do not change it depending on whether a particular project looks comfortable.
Keep a project decision note
Project / review date / figures read at:
Current scope and agreed plan:
Reviewed hours used:
Remaining tasks and estimate:
Working forecast and difference from plan:
Delivery state and supporting reference:
Changed assumption or dependency:
Open scope or billing question:
Decision made, or decision still needed:
Owner / next action / deadline:
Client communication needed / owner:
What we will check at the next review:Write the decision in the project's ordinary record and send the relevant portion to the client through the agreed channel. A staffing question belongs with the people arranging capacity; an unapproved scope change belongs with the engagement owner and client. Avoid distributing internal screenshots, private prompts or individual activity judgments as a project status report.
Check whether last week's decision happened
Open the next review with the previous decisions that are due. If an estimate remains uncertain, state what will reduce that uncertainty: a short investigation, a client answer or a review of the proposed solution. The purpose is to make the next commitment more informed, rather than to produce a more confident-looking spreadsheet.
Colabio's agency time tracking connects project time, budgets, reviewed timesheets and client invoices. The project management page explains planned hours and remaining-task forecasts. Read those figures alongside the team's updates, and use the budget variance guide and client invoice guide for the detailed follow-through. Keep the final scope and delivery decisions with the people responsible for the engagement.