Set weekly capacity from the team’s actual schedules
Start with scheduled hours for the week. Remove holidays and approved leave for each person. Then reserve expected team meetings, on-call support and other commitments that already occupy that window. Use the same treatment for recurring work across members. If a meeting is part of the project estimate, count it in the estimate or the capacity reserve once.
Mark one owner for the estimate to finish and one owner for each handoff. Begin with the work already in progress and the delivery dates it supports. If a workstream is uncertain, record a small range and the event that changes it, such as the customer confirming a test environment. Keep contingency visible so it can be used for real changes.
Team, dates and reporting time zones:
Scheduled hours, holiday and leave by person:
Known meetings and support reserve:
Available delivery hours by role:
Open work, remaining effort and assignee:
Specialist reviewer, local review windows and deadline:
Expected contingency and what may use it:
Tradeoff, decision owner and next check:Work through a team with 63 hours and one review bottleneck
| Role | Schedule and reservations | Available | Allocated |
|---|---|---|---|
| Ari, backend | 40 scheduled − 8 leave − 5 meetings − 4 support | 23 h | 18 h |
| Bea, frontend | 36 scheduled − 0 leave − 6 meetings − 6 support | 24 h | 18 h |
| Cam, release reviewer | 32 scheduled − 8 leave − 4 meetings − 4 support | 16 h | 10 h |
| Team | 63 delivery hours after reservations | 63 h | 46 h |
The team has 17 hours unallocated. Ari’s change still needs three hours of review with Cam before Thursday’s release sign-off. Cam has six hours unallocated over the week but only two one-hour windows before the sign-off. The team can move the sign-off to Friday, arrange a qualified backup, or reduce the release scope and get a revised review estimate.
Record the chosen option with a checkpoint, such as Wednesday at 15:00 UTC. If no backup has confirmed by that time, the release lead switches to the Friday plan. See the meeting load audit for converting required calls into occupied hours when your team’s calendars overlap.
Ari’s five free hours and Bea’s six can help with work either person can do, such as preparing the test fixtures or updating the customer notes. Put that work on the plan with its own cap. If the reviewer needs an uninterrupted session, schedule one early enough to leave time for a change and a repeat review. Available hours across the whole team hide this sequence unless the plan shows who hands off to whom.
Use the midweek review to update the plan
- Check finished work, open blockers and who is assigned. Ask owners to update remaining effort against the current acceptance conditions.
- Compare the revised effort with each person’s hours and the timing of review and handoffs. Name the next decision before adding work.
- Compare tracked and planned time to find the estimate or support assumption that changed. Keep the plan version so the next week’s discussion can learn from it.
- Leave a brief note about the work you moved and the new date or owner. Publish it in the weekly team status update.
Use the team capacity calculator for the initial schedule and leave check. Colabio’s capacity and leave guide explains the availability behind utilization, while the project Budget card compares tracked time and open estimates with planned project hours. Book a Colabio demo to see those views for a team planning or review workflow.