How the calculation works
Scheduled team hours = people × weekly hours × weeks. Available hours subtract the team's holiday hours and other leave. Meetings then allocate part of that available time, leaving capacity for the project work entered separately.
Project balance = available hours − meeting hours − planned project hours. A negative balance is a shortfall. Meetings belong inside available hours; they are not additional leave. If your project estimate already includes those meetings, remove them from one input to avoid counting them twice.
A worked two-week example
This illustrative team has five people scheduled for 40 hours a week over two weeks: 400 hours. One eight-hour holiday per person removes 40 hours. Another 24 hours of team leave leaves 336 available hours. Thirty meeting hours leave 306 hours for project work.
Planning 280 project hours leaves 26 hours unallocated. Planning 320 project hours creates a 14-hour shortfall. Neither result predicts delivery: interruptions, review, uncertainty and the estimate itself still need a discussion.
Use the same period and avoid duplicate deductions
- Use people with the same schedule in one scenario; calculate different schedules separately.
- Count only holiday hours that fall on scheduled working time.
- Exclude holiday hours from the other-leave total.
- Use team totals for leave, meetings and project work, all within this period.
- Do not promise every unallocated hour; review the plan with the people responsible.
Take the plan into a weekly review
Colabio's capacity views compare tracked time with available time based on expected hours, organization holidays and recorded leave. This public tool is a separate manual scenario. It does not read a calendar, change anyone's schedule or establish a productivity score.