How the forecast works
Forecast hours = actual hours + estimated remaining hours. Forecast variance = forecast hours − planned hours. A positive variance is over budget; a negative one is under. Percentage variance divides that difference by planned hours and is unavailable when the planned budget is zero.
The cost figures multiply hours by one blended rate in US dollars. They are planning estimates, not a client invoice or a profit calculation. Different member rates, expenses, taxes, discounts and fixed-price contracts need their own treatment. The calculation runs in your browser and the calculator has no submission or storage function. The input and result region is masked for session recording; the site's analytics and cookie policy still applies.
Example of an early scope warning
A studio agrees 100 hours for a client portal. It has spent 70 hours and estimates another 45 hours for testing and release. The forecast is 115 hours, 15 hours or 15% over budget. At a planning rate of $100 per hour, that is $11,500 against a $10,000 hours budget.
Thirty budget hours remain, but that does not mean the unfinished work takes thirty hours. Review whether the extra work is an approved scope change, an underestimated task or rework. Keep the agreed baseline and any changed forecast visible rather than silently rewriting the original budget.
Compare three decisions on the same project
Keep the original 100-hour plan in the review record. Change the calculator inputs only when a work estimate or an approved scope decision changes.
- Keep the current plan
- 70 hours worked plus an estimated 45 for a 115-hour forecast. The project is 15 hours over the 100-hour plan.
- Approve a 12-hour change
- The budget becomes 112 hours. If the 115-hour forecast already includes that work, the project is now 3 hours over.
- Move 10 hours to another phase
- If the current 100-hour budget stays in place, the updated 35-hour remaining estimate gives a 105-hour forecast, 5 hours over.
Name the person who can approve a different scope, the date of the decision, and which phase now owns any deferred work.
What to review before acting
- Use reviewed project time and resolve open corrections or overlapping entries.
- Ask the people responsible to estimate unfinished tasks, including review and testing.
- Separate new scope from an estimate change, and record the decision.
- Revisit the forecast when the scope or remaining-work estimate changes.