How the forecast margin is calculated
Multiply each role's hours worked by its internal hourly cost. Do the same for estimated hours remaining. The calculator rounds each result to the nearest cent, rounding half a cent up. Add those results and other direct costs to get the forecast cost. Subtract that cost from the fixed fee for the project contribution. Divide contribution by the fee to find the forecast contribution margin.
Use the approved fee and an agreed cost basis for the same scope. Include a vendor or materials expense once. The currency selector labels the figures you enter. For accounting records, reconcile the same period and cost basis with the team's financial report. QuickBooks project labor cost guidance explains the distinction between hourly costs and payroll expenses.
A $12,500 fixed-fee agency example
A fictional studio has spent 18 design hours at $75, 42 engineering hours at $95 and six testing hours at $60. That is $5,700 of labor to date. It estimates eight more design hours, 20 engineering hours and 10 testing hours. Those add $3,100. Add $600 in project expenses for a $9,400 forecast cost.
The $12,500 fee leaves $3,100 of forecast contribution, or 24.8%. In the engineering row, change remaining hours from 20 to 28 to model an extra eight hours. Cost rises by $760 and the margin becomes 18.72% at the same fee. Record whether the extra work belongs in the current scope and who owns that decision.
Update the estimate when the work changes
Ask each owner for the work that remains, including review and release. Use a scope change request when the client needs to decide. If a cost estimate is too uncertain, compare the likely effort with a second scenario and set a date to update the assumptions.
The fixed-fee agency workflow shows which records support a project review. The project budget calculator helps check hours against the agreed scope. Book a Colabio demo to walk through how tracked task time and remaining estimates feed that review.