Set up time categories against the agreed work
Turn the agreed scope into a handful of workstreams with owners and acceptance criteria. Map the proposal’s role estimates into those workstreams. Add named categories for coordination, rework and approved changes when those categories will support real decisions. Avoid giving the team so many codes that a five-minute task needs a classification meeting.
Route ambiguous entries to a reviewer. A record labeled “client revisions” could reflect included feedback, a correction or an approved expansion. Ask the contributor for the task and the reviewer for the classification. Review those hours with all worked hours while the issue is open so that delivery effort remains visible.
Combine reviewed effort and the current forecast
A fictional studio has a $12,000 fixed fee and plans an internal direct labor budget of $6,000. Its rates below are assumed internal costs, with hours reviewed at the end of week two. Estimates to finish come from task owners after reviewing the remaining deliverables.
| Role and hourly cost | Reviewed hours and cost | Hours and cost to finish |
|---|---|---|
| Design at $65 | 20 h, $1,300 | 4 h, $260 |
| Engineering at $85 | 30 h, $2,550 | 18 h, $1,530 |
| Project management at $60 | 6 h, $360 | 4 h, $240 |
| Total | 56 h, $4,210 | 26 h, $2,030 |
The forecast is 82 hours and $6,240 of direct labor. That exceeds the internal budget by $240. The fee less projected direct labor is $5,760, or 48% of the fee before any other costs. If you use this view for actual project margin, include applicable delivery expenses and agree how overhead and rate changes will be treated. Consistent definitions make comparisons across projects meaningful.
Use the fixed-fee project profitability calculator to enter the reviewed and remaining hours by role. Add the team's approved direct costs and change the remaining estimate to see how the contribution changes.
The studio still invoices according to the agreed fee and milestones. If a signed change adds fees or new milestones, update the client-facing record from that approval. Keep a reference to the decision alongside the internal time review.
Choose a response to the forecast
The lead can check whether the engineering forecast covers an accepted deliverable or a newly requested integration. If the integration was agreed already, the team may need to change sequence, find capacity, or revise the internal budget. If the client requested it separately, capture the decision using the scope change template and estimate the added work separately.
Keep the previous forecast in the review notes. The reason for the change matters when quoting similar projects: an omitted testing task, an extra review cycle and a new deliverable all call for different adjustments in the next estimate. Give each unresolved item an owner and review date.
Run a sensitivity check on work with an uncertain finish. In the studio example, six more engineering hours cost another $510 at the assumed rate. That moves the total to $6,750 and raises the variance to $750. Ask the person estimating the work what could trigger the extra six hours. If the trigger is a pending client input, name the date by which the lead will escalate it.
Run a fixed-fee review every week
Current scope and accepted fee reference:
Reviewed hours by workstream and unassigned hours:
Remaining hours with owner and assumptions:
Forecast direct labor cost and variance from budget:
Other expenses included in the margin view:
Scope, staffing or budget decision and deadline:
Client update or change approval reference:Colabio’s agency time tracking and time budget review guide help connect the current hours to a project review. For teams with multiple fixed-fee accounts, book a Colabio demo and bring a budget you want to review from estimate through tracked hours.