Copy the agency hours estimate worksheet
Client, opportunity, version and estimator:
Deliverable and acceptance criteria:
Workstream, owner or role, hours and basis:
Client inputs and required dates:
Included review rounds and test scope:
Risk scenario, extra hours, trigger and mitigation:
Assumptions and unresolved questions:
Earliest start by role and milestone dependencies:
Approved version and first estimate review date:List the deliverables in the same language as the client brief. For a web build, include setup, stakeholder reviews, accessibility checks, fixes and handover. Ask each role which part of the acceptance criteria drives its hours. For small jobs, the estimator can collect estimates in one conversation and record what the team assumed about feedback and handover.
Look at comparable completed work where possible. Separate a reusable component from a custom one, and compare the number of revisions or integrations. If the last project ran over because a client changed its brief, keep those hours for reference and record their reason before deciding how much applies here.
Estimate a small build by role
A fictional agency is estimating a five-page marketing site. The team expects client-provided copy, one stakeholder review per stage, and reuse of an existing form. Its base case has 62 labor hours. The account lead wants to know how much a second round would add before promising a date.
| Role or workstream | Base hours | Extra round |
|---|---|---|
| Project lead and coordination | 8 | +2 |
| Design and responsive layouts | 16 | +4 |
| Build and form setup | 26 | +3 |
| QA and handover | 12 | +1 |
| Total | 62 | +10, for 72 hours |
The 10 extra hours assume consolidated feedback changes two layouts. If the change adds a new page or integration, write a new estimate for that request. Use the scope change request template to capture added deliverables and their effect on the first release.
Check the date against capacity
A 62-hour effort does not map directly to a delivery date. If the builder has 12 available hours next week and 16 the week after, 26 hours already span two weeks. If design approval arrives after the first week, recheck the start and the slot for QA. Plan using the actual sequence of dependencies, including client review time.
Compare planned allocation with active projects and leave in the weekly agency capacity review. Confirm that the proposed start still works when the statement of work is accepted. For shared specialists, assign the person who resolves conflicts across accounts and name the date by which they need the client’s decision.
Put dependency dates beside the work. Suppose the client needs three business days to approve design and the available builder changes projects the following Monday. A Wednesday delivery of design may miss that builder’s window. Identify the last useful review date, agree what can start before design is signed off, and show when the next capacity window opens. Update the estimate version if a change in staffing also changes the hours.
Give delivery a baseline it can maintain
- Save the approved estimate with the same categories the team will use for tasks and time entries. Record the client inputs and review rounds assumed.
- Ask each lead to confirm the scope, planned hours and handoff date. Add any immediate uncertainty to the first project review instead of leaving it in the quote notes.
- At the first checkpoint, compare reviewed hours and remaining effort with the baseline. If the total moves, explain which assumption changed and who decides next.
Colabio’s agency time tracking links time with projects and tasks. Use the blended versus role-rate example to see how the same hours affect a draft when the mix shifts. If you want to test the quote-to-delivery handoff with your workflow, book a demo and bring a recent project estimate.