Check what your client agreed to pay
A blended rate is a single client rate across a defined scope of work. A role-rate agreement applies separate rates to specified work or contributors. Record the currency, covered scope, dates and rate basis in the quote. If finance builds a blended estimate from several roles, keep those role assumptions next to the total so a staffing change is easy to explain.
Check which rate rule your software can represent. Harvest’s rate documentation distinguishes project, person and task rates. In Colabio client invoices, the project rate applies unless a member has a rate set on that project. If the same person performs two differently priced roles, confirm how your finance team represents that split before promising the invoice format.
A role’s bill rate describes the client charge. A labor cost rate describes delivery cost. Keep those fields and their permissions separate. Use the agency hours estimate template to record who is expected to do the work and how many hours each role needs.
Reconcile two drafts against the same ten hours
This fictional project was estimated at six design hours at $100 per hour and four development hours at $175. The total is $1,300 for ten hours, so the weighted estimate is $130 per hour. The team actually works four design hours and six development hours. All ten hours are reviewed and eligible under the respective example agreement. All amounts are USD before taxes or fees.
| Work | Reviewed time | One $130 rate | Separate role rates |
|---|---|---|---|
| Design | 4h | $520 | $400 at $100/h |
| Development | 6h | $780 | $1,050 at $175/h |
| Draft subtotal | 10h | $1,300 | $1,450 |
The role-rate draft comes to $1,450. Its $150 difference comes entirely from two hours shifting from the $100 role to the $175 role. If the signed agreement uses the $130 blended rate, the draft stays at $1,300. Use the billing cap example when the agreement also limits the charge.
Suppose labor costs $60 per design hour and $105 per development hour. Direct labor rises from the planned $780 to $870. The $1,300 blended invoice leaves $430 after that direct labor cost and before overhead. Use the actual costs and time for internal planning, and keep the invoice at the agreed rate.
Have a second reviewer reproduce the draft
Client, project, dates and currency:
Agreement and confirmed rate basis:
Expected mix, actual reviewed hours and names or roles:
Project rate and any intentional member override:
Draft subtotal, differences, reviewer and approval reference:
Internal delivery cost and next estimate adjustment:On a blended project, check for member rates left over from a copied setup. On a project with different member rates, confirm one line for each contributor against the agreement. If you change a rate, refresh the draft and check its preview before issue. Ask a second person to reproduce the amount from reviewed time and the rate settings. Bring the ten-hour example to a Colabio demo to try both setups with your team.
For the next estimate, record whether the extra development hours came from an expected skill mix or a lasting scope change. Forecast the remaining development work with the agreed staffing plan and then route any price change through the account owner. Keep the old quote and the approved change together so the next invoice reviewer can tell which rate covers which work.
Catch a copied member rate before it reaches the client
Suppose the $130 blended project was copied from another engagement and still has the developer’s $175 member rate. The preview shows $520 for design and $1,050 for development, totaling $1,570. The extra $270 is six hours multiplied by the $45 rate difference. Correct the unintended override, refresh and verify that both lines use $130 and the subtotal returns to $1,300.
Keep a brief record of why the draft changed and which approved rate applies. If a rate adjustment affects work from a prior period, confirm the period and review the existing invoice before editing any new draft. Use the guide to corrections after invoicing when the underlying time also needs review.