Put one fixed-fee project in both trials
Use a fictional $16,000 website rebuild that lasts six weeks. Its payment schedule is $8,000 at kickoff and $8,000 at client acceptance. The agency still incurs costs in weeks with no invoice. Ask the delivery lead, billing owner and contributor to work in their normal roles. Write down what each should be able to see before inviting them.
Enter 40 design hours at an internal cost of $70, 68 development hours at $85 and 12 delivery hours at $65. Add a $350 expense for test devices. Labor is $9,360, total stated cost is $9,710 and the fictional project's contribution is $6,290, or 39.3% of the fee. Use the fixed-fee project profitability calculator to check those figures with the same inputs.
At the end of the pilot, add four developer hours for an accessibility correction that was already covered by scope. Cost rises by $340 to $10,050. The fee stays $16,000, so contribution falls to $5,950, or 37.2%. Ask the project owner to show where those four hours appear and whether the invoice amount stayed the same.
Compare each product during the review
| Question | Teamwork.com | Harvest |
|---|---|---|
| Where does a contributor log the correction? | Try logging it on a project task with the original acceptance detail. | Log the work in the project and task category. Keep the original decision accessible from the time note or your work tracker. |
| How does the delivery owner see the cost? | Check the Finance section, budget and profitability report for that project. | Check the project analysis or profitability report on the intended plan. Confirm member rates and project dates. |
| How does the billing owner handle the fee? | Create a fixed-price project invoice and check export to the accounting tool in your trial. | Create the two fixed-fee milestone payments and check the invoice associated with the completed milestone. |
Teamwork.com's project setup guide and profitability workflow document the tasks, budgets and reports used here. Review its invoice permissions before granting billing access. A role that can create an invoice can also receive related time and rate permissions.
Harvest documents fixed-fee milestone invoices and fixed-fee revenue and costs in its profitability report. The latter is available to admins on Harvest Enterprise. Check the actual product and plan if the project lead needs reporting access without broader administration.
Compare over the whole six weeks first. A report for the middle two weeks can spread revenue across dates or count the fee according to different settings. Record the date range and revenue treatment next to the report. Read Teamwork.com's financial report calculations and check the equivalent Harvest report before treating two margin percentages as directly comparable.
Decide using the closeout, then record the result
Project fee and invoice milestones:
Original task and correction link:
Tracked cost before and after correction:
Report date range and revenue method:
Who can see internal costs:
Where client acceptance is recorded:
Who can create or export the next milestone invoice:Run the handoff with the person who prepares the next invoice. Can they confirm acceptance, find the change and identify the payable milestone without asking the original project lead? Teamwork.com is a candidate when that owner also needs to manage project delivery in the same system. Harvest is a candidate when your delivery workflow already works and the team mainly needs time and invoicing.
If your recurring issue is reviewing time with the original task and sharing a controlled progress update, add Colabio to the same pilot. Verify client invoice behavior and the client progress page using your own example. Keep the agreed fixed-fee schedule explicit. Book a demo to walk through the review and recipient roles with your team.